Summary:
Labour shortages, material delays, and increased
transportation costs, caused by tariffs are giving developers legal grounds to
invoke delay clauses in pre-sale contracts. These clauses allow the
developer to push out the completion date by a period equal to the delay caused
by such events, even
after issuing a Completion Notice! Translation: At the time
of contract signing, buyers and sellers may not actually know when the building
will be finished.
The Delay Clause in Action
Here’s a typical clause found in many pre-sale
agreements:
“The Developer
shall be entitled to extend the Completion Date by a period equivalent to any
delay arising from strikes, lockouts, fire, flood, labour or material
shortages, tariffs, transportation delays, governmental actions, or any other
event beyond the reasonable control of the Developer.”
You’ll find this language under headings like
“Permitted Delay”, “Extension of Completion Date”, or “Force Majeure.”
BUT WAIT… Shouldn’t Tariffs
Lower Prices?
Interestingly, there’s another side to this story.
Some economists argue that tariffs may lead to short-term over-supply,
especially if developers have pre-purchased materials or if buyers begin to
hesitate.
An increase in inventory—whether from stalled
construction or cautious buyers—can push prices downward, as sellers are
motivated to move unsold units.
This means your clients may be paying more for
uncertainty in completion timing, but potentially less per square foot if
market prices soften. It’s a strange paradox that underscores the importance of
reading the fine print.
Takeaway
Tariffs are doing more than raising costs—they're
introducing legal and market uncertainty into pre-sale deals. From delay
clauses to price shifts, your clients need your guidance more than ever. Stay
informed, ask good questions, and work with the right professionals to keep
deals—and relationships—on track.